01Licensing procedure and document preparation
-
- Technical review
- Submit to Gas Safety Corporation
- Documents: Technical review application (Use the format provided by Gas Safety Corporation), technical review
- Relevant laws: Annex 5 of high-pressure gas related laws (Standards for the facilities and technology for the general manufacturing of high-pressure gases)
-
- Permission application
- Submit to the administrative department of the city or county office
- Documents: Application for permission to install storage (Use the required format)
-
- Application for interim inspection
- Submit to Gas Safety Corporation
- Documents: Application for interim inspection (Use the format provided by Gas Safety Corporation) and drawings
-
- Application for completion inspection
- Submit to Gas Safety Corporation
- Documents: Application for completion inspection (Use the format provided by Gas Safety Corporation) and drawings (including pipeline ISO)
- Equipment: Non-destructive testing equipment (Commercial company is hired in general), airtight booster
02Timeline
Task/day | 5 | 10 | 15 | 20 | 25 | 30 | 35 | 40 | 45 | Note |
---|---|---|---|---|---|---|---|---|---|---|
Drafting technical review | KGS | |||||||||
Completing technical review | KGS & city and county offices | |||||||||
Completing permission | City and county offices | |||||||||
Installing storage | ||||||||||
Requesting interim inspection | KGS | |||||||||
Interim inspection | KGS | |||||||||
Requesting completion inspection | KGS | |||||||||
Completion inspection | KGS | |||||||||
HR management guidelines | KGS & City and county offices | |||||||||
Report for use | City and county offices |